Industrial construction
Improvements of mechanical alterations production plant till 2400Mg/h in Bogdanka
Scope of works: delivery and erection of steel constructions of cubature buildings and conveyor bridges.
Quantity: 2500 tons.
Realisation time: start November 2010,
finish April 2012.

Deadline for completion: 14 months