Industrial construction
Construction of the flue gas denitrification system for units No. 1, 3 and 5 in Jaworzno III Power Plant
Deadline for completion: 14 months
Scope of work: comprehensive disassembly, prefabrication, delivery and erection of steel structures and insulation for SCR systems of units No. 1, 3 and 5 with a total weight of approximately 3000t.
Realization time: start September 2019.
Finish October 2020.