Construction of the 3rd stage of flue gas desulphurization system and the 1st stage of the flue gas denitrification system for the WR-25 boiler house in PEC Gliwice
Deadline for completion: 11 months
Scope of work: comprehensive disassembly, prefabrication, delivery and erection of steel structures and insulation for flue gas desulphurization and denitrification systems with a total weight of approximately 500t.
Realization time: start September 2020.
Finish July 2021.
Deadline for completion: 14 months