Scope of work: erection of steel construction of ducts- desulfurize and non- desulfurize from the three- way pipe to the funnel H200 with the secondary steel construction and erection of installation: silencer, flap, compensator and heater of flue gas.
Quantity: 3736 tons.
Realisation time: start March 2010,
finish: August 2011.